Project Details:
Our scope of services was not limited to transport but the loading at Port and custom clearance was also under our scope of services.
Details are mentioned below:
- POL: Shanghai
- POD: Karachi Port Trust (KPT)
- Final Destination: HUB Power Plant
- Number of Units: 8 (6 Concrete Mixer Truck & 2 Concrete Pump Truck)
- Total Distance: 55 kms from Karachi Port to HUB Power plant
- Heaviest Unit: 34 tons with the height of 13 feet’s